Contact Us

646.532.3696

Columbia NW Science Corner Building - 10th and 11th Floor Fit-Out

Last Updated: 2/2/13

Status: In Construction

Gallery
Start Date: 02/01/14 | Finish Date: 02/27/15

Description:

CU NWSB is a labortatory fit out of an existing building.  The 10th and 11th floors are vacant and we will be installing the plumbing services. 

Key item to this project is coordination of laboratory benches as we have many services located within the benches. 

This project has acid waste, RO water and SS swagelock piping but 90% all lab gas piping is copper L tube.